Silicon Labs is discontinuing 131 EFM32 and EFR32 Series 1 microcontrollers and wireless SoCs, 261 ordering codes once the -R reel variants are counted, under End of Life notice #2026-05-13-1811. The last order date is 19 November 2026 and the last ship date is 19 May 2027. The notice lists a Series 2 replacement for almost every part, and it marks every one of those replacements "Drop-in Compatible: NO". This page maps each family to its replacement and covers the parts with no successor at all. It also helps you decide, in the days left, between a last time buy and a redesign.
What the notice covers and the three dates that matter
Notice #2026-05-13-1811 covers eight families: EFM32 Giant Gecko GG11 and GG12, Tiny Gecko TG11, Jade Gecko JG1 and Pearl Gecko PG1, plus the EFR32 Blue Gecko BG1, Flex Gecko FG1 and Mighty Gecko MG1 radios. The stated reason is that customer demand no longer meets the minimum manufacturing requirement. In other words, a volume decision, so there is no quality problem to fix.
- 13 May 2026 (EOL issue date): every order placed after this date is non-cancellable and non-returnable (NCNR).
- 19 November 2026 (last order date): Silicon Labs stops accepting orders. Orders placed before 13 May also become NCNR on this date.
- 19 May 2027 (last ship date): every order needs a customer requested delivery date on or before this date. Silicon Labs no longer accepts a delivery date beyond it.
Two clauses matter for planning. LTB orders are built to order and may carry extended lead times. Silicon Labs also says it accepts orders before the cutoff but does not guarantee to fill all or part of them. A last time buy placed on 18 November is a request for parts, and the factory may not fill all of it.
The replacement map: every Series 1 family and its Series 2 target
Every Series 1 MCU in the notice moves to an EFM32 Series 2 Pearl Gecko built on the Arm Cortex-M33 (PG22, PG23, PG26 or PG28), and the radios move to BG22, FG23 or MG24. The table summarises the notice's own replacement column. Base part counts exclude the -R reel duplicates.
| Series 1 family (core) | Base parts on notice | Replacement named in the notice | Typical package change |
|---|---|---|---|
| EFM32JG1 Jade Gecko (Cortex-M3, 40 MHz) | 6 | EFM32PG23B200 / B210 (F128 or F256) | QFN32 to QFN40, QFN48 stays QFN48 |
| EFM32PG1 Pearl Gecko (Cortex-M4, 40 MHz) | 7 | EFM32PG23B200 / B210; 1 part has none | QFN32 to QFN40, QFN48 stays QFN48 |
| EFM32TG11 Tiny Gecko | 17 | EFM32PG23B210, PG28B300, PG26B101, PG22C200 | QFP48/QFP64 to QFN48/QFN68 |
| EFM32GG11 Giant Gecko (Cortex-M4) | 28 | EFM32PG26B301 (F2048 or F1024), PG28B310 | QFP64/QFN64 to QFN68; BGA112-192 to BGA136 |
| EFM32GG12 Giant Gecko (Cortex-M4) | 34 | EFM32PG28B310 / B300, PG26B301 / B101 | QFP64 to QFN68; BGA to BGA136 |
| EFR32BG1 Blue Gecko | 12 | EFR32BG22L122 / C224; 2 parts have none | QFN32 stays QFN32 or moves to QFN40 |
| EFR32FG1 Flex Gecko | 19 | EFR32FG23A010F256 (GM40 or GM48) | Targets are QFN40 or QFN48 |
| EFR32MG1 Mighty Gecko | 8 | EFR32MG24A021 / B020 F1024 | Targets are QFN40 or QFN48 |
The flash size is in the ordering code: F256 means 256 kB and F2048 means 2048 kB. That is the fastest check that a proposed replacement is not a memory downgrade. If the -R suffix and the other characters in the code are unfamiliar, our part number suffix decoder explains how they work.
Why none of the 261 codes is a drop-in swap
Every row in the notice says "NO" under drop-in compatible, for four reasons a buyer can check without opening a schematic:
- Footprint. A Jade Gecko EFM32JG1B200F256GM32 in QFN32 maps to EFM32PG23B200F256IM40, a QFN40. Most Giant Gecko QFP64 parts map to QFN68. A leaded QFP to a QFN is a new land pattern, a new stencil and, for the hidden QFN joints, X-ray or AOI inspection on the line.
- Temperature grade. In Silicon Labs ordering codes, G means -40 to 85 °C and I means -40 to 125 °C. Many G-grade Series 1 parts map to I-grade Series 2 parts. That is an upgrade on paper, but every replacement is a different part number that has to be released in your system.
- Core. Series 1 runs a Cortex-M3 or M4, and the Series 2 targets run a Cortex-M33. Arm describes the M33 as an Armv8-M core with optional TrustZone security. Code recompiles, but the startup files, interrupt handling and peripheral drivers change.
- Tooling. The notice states that after its effective date, EOL parts are no longer available for new projects in Simplicity Studio. Existing Series 1 firmware builds still work, but you should archive the exact SDK and compiler versions now while they are easy to get.
Practitioner gotcha: the "R" at the end of a code is only the reel version. Parts from a reel and from a tray have the same die and the same EOL date. The EFM32PG23B200F256IM40-C and -CR share one replacement row, so do not treat the reel code as a separate second source. Our tape and reel guide covers how packaging changes the MOQ.
Three parts with no replacement at all
Three base parts, five ordering codes, show "NA" in the replacement column, so Silicon Labs names no successor for them:
- EFM32PG1B100X1271GM32-C (and -CR)
- EFR32BG1B132F256GD1-C0
- EFR32BG1P332F256GJ43-C0 (and -C0R)
None of the three follows the pattern of the rest of the list: X1271 sits where a flash code such as F256 normally goes, and GD1 and GJ43 replace the usual GM32 or IM48 package code. Ask your Silicon Labs contact what they are before you size the buy. If one of these is on your BOM, a last time buy is the only route that avoids a redesign. Plan the quantity against the remaining product life, not against next year's forecast.
Last time buy or redesign: a worked example
Take a German meter or sensor maker that builds 4,000 units a year on EFM32JG1B200F256GM32-C0 and must keep the product in production until the end of 2030. That is four years of demand after the last ship date. The LTB arithmetic looks like this:
- Demand from mid-2027 to end-2030: about 3.5 years x 4,000 = 14,000 parts
- Assembly scrap and test yield at 3%: +420
- Field service and repair stock at 2%: +280
- Total LTB: about 14,700 parts, all NCNR, delivered before 19 May 2027
Weigh that against the redesign to EFM32PG23B200F256IM40-C: a new QFN40 layout, firmware ported to the Cortex-M33 and most likely a repeat EMC test if the product carries CE marking. The LTB ties up cash and storage for four years, and QFN parts in storage need moisture control (see our MSL guide). The redesign costs engineering time once and resets the lifecycle clock. A common split is to buy enough Series 1 to bridge 18 to 24 months while the PG23 board is qualified, not to buy the whole remaining life. Our last time buy strategy guide covers the buffer maths in more depth.
Leaving Silicon Labs: when a cross-vendor part makes sense
A redesign is also a chance to second-source the MCU. A team that has to re-layout and re-port the firmware anyway can look at another vendor at little extra cost. Two parts in GlobX stock show the trade-offs, both checked as of November 2026:
- ST STM32L151RBH6ATR: an ultra-low-power Cortex-M3 with 128 kB flash in a 64-ball BGA. It is the same core family as the Jade Gecko, so the timing and math code carry over more easily. GlobX holds 19,000 pieces, date code 22+, part status Active. The trade-offs are 32 MHz against 40 MHz, half the flash of an F256 Jade Gecko, and a BGA your line must be able to place and inspect.
- ST STM32G491CCU3: a Cortex-M4F at up to 170 MHz with 256 kB flash in UFQFPN48, rated -40 to 125 °C. It suits Pearl Gecko designs that used the M4 for signal processing and are mains-powered. GlobX holds 5,500 pieces, date code 22+. It is built for performance, not for years on a coin cell, so it is not a battery-life replacement.
For coin-cell products, staying with Silicon Labs Series 2 is usually the lower-risk path. Silicon Labs built the Gecko line around low-energy modes that most general-purpose MCUs do not match. The M33's TrustZone also matters for products that fall under the EU Cyber Resilience Act, whose main obligations apply from 11 December 2027. See our CRA sourcing guide.
What to do in the eight days before 19 November
- Search your BOMs and ERP for the prefixes EFM32GG11, GG12, TG11, JG1, PG1 and EFR32BG1, FG1, MG1. Check each full code against the notice, because not every Series 1 variant is listed.
- Flag the three no-replacement parts first. They have no redesign fallback.
- For every other part, decide between a full LTB and a bridge buy plus a Series 2 redesign. Then place the factory order with a delivery date before 19 May 2027.
- After the last ship date, buy only traceable stock, with original reels, date codes and a CoC. Our counterfeit avoidance guide lists the checks.
If your ordering code is on the notice and the factory window is too tight, send GlobX the code, the quantity and your required date. We will come back with traceable Series 1 stock, the Series 2 replacement, or a cross-vendor option, whichever your timeline allows.